A Quick Update On The Hunt/Gantzel Project

  • Work is currently taking place in the south end of the project, from Johnson Ranch Boulevard/Gantzel Road to Magma Road in Hunt Highway to construct improvements.  Current work includes utility work on the west side of Hunt Highway, with Hunt remaining open for travel, one lane in each direction, with traffic shifted away from the work zone.
  • Scheduled to take place later this week, final striping of Judd and Tourmaline Roads will take place so they can be opened for travel by or before Friday.
  • Please note – the County is fully aware of the potholes that have formed on the temporary asphalt, from Quartzite to Gantzel.  They will continue to monitor and repair them as needed.  In the meantime, slow speeds (25 mph through the work zone) are greatly appreciated to help limit the effect to the driver.

Business and resident access is being maintained, and we thank you for your continued patience during this construction.

For project questions or information:  480.898.4100 or visit www.HuntGantzel.com