Be advised, with the rain and poor conditions, roadwork deadlines may be delayed. 

  1. Power Rd NB and SB lane shifts between Ocotillo Rd and Brooks Farms for road improvements. Jan. 16 – Mar. 04; 8:30 am – 2 pm 
  2. Rittenhouse Rd NB lane shift between Combs Rd and Railroad Spur crossing for roadway widening. Feb. 01 – Apr. 01; 24-hour 
  3. Queen Creek Rd EB and WB lane shift at Ellsworth Rd for road widening work. Feb. 06 – Mar. 04; 24-hour 
  4. Power and Ocotillo Rd intersection closure for street light install, grading, paving and striping. Mar. 01 at 8 pm to Mar. 04 at 5 am 
  5. Riggs Rd EB lane shift at Ellsworth Rd for paving work. Feb. 21 – Feb. 27; 24-hour 
  6. Queen Creek Rd EB lane shift between 220th St and Meridian Rd for sewer main install. Feb. 25 – Mar. 22; 24-hour 
  7. Cloud Rd EB and WB lane shift between Rittenhouse and Crismon Rd for utility work. Feb. 7 – Mar. 30; 24-hour 