With 21 different road projects taking place last week residents have some good news with 15 of the projects completed or scheduled to be completed by June 30th. Take note of what has been completed and what is still underway for your commuting and holiday travels. Additionally, there are two projects that begin this week.

  1. COMPLETE ON JUNE 30TH – Cloud Rd EB and WB lane shift between Rittenhouse RD and Crismon road for water and sewer line install. Apr. 16 – Jul. 30; 24-hour
  2. COMPLETE ON JUNE 30TH – Market Place Dr full closure at 187th St for utility work. May 8 – Jun. 30; 8:30 am – 4 pm
  3. COMPLETE ON JUNE 30TH – Rittenhouse Rd NB lane shift at 187th St for utility work. May 6 – Jun. 30; 8:30 am – 4 pm
  4. COMPLETE ON JUNE 30TH – Rittenhouse RD NB and SB lane shift between Power Rd and 187th St for utility work. May 6 – Jun. 30; 24-hour
  5. COMPLETED – Ocotillo Rd EB lane shifts between Signal Butte Rd and 226th St for fiber work. Jun. 20 – Jun. 28; 8:30 am – 3 pm
  6. Hawes Rd NB and SB lane shift between Chandler Heights Rd and Via De Arboles for traffic light install. May 31 – Jul. 16; 8:30 am – 4 pm
  7. BEGINS JULY 2 – Rittenhouse Rd NB lane shift at Combs Rd for road alignment work. Jun. 02 – Jul. 07; 24-hour
  8. BEGINS JULY 2 – Combs Rd full closure between Rittenhouse Rd and Meridian Rd for road alignment work. Jun. 02 – Jul. 07; 24-hour
  9. COMPLETED – Germann Rd EB and WB lane shift between Ellsworth Rd and 210th St for ramp install, grading, and paving. Jun. 11 – Jun. 28; 24-hour
  10. COMPLETED – Chandler Heights Rd WB shoulder work between Power Rd and 188th ST for utility work. Jun. 10 – Jun. 28; 8:30 am – 4 pm
  11. Meridian Rd SB lane shift at Via Del Jardin for utility work. Jun. 15 – Dec. 31; 24-hour.
  12. Signal Butte NB and SB lane shift between Ocotillo Rd and Escalante St for utility work. Jun. 17 – Jul. 05; 24-hour
  13. COMPLETED – Ellsworth Rd SB lane shift between Walnut Rd and Ryan Rd for sidewalk install. Jun. 24 – Jun. 28; 9 am – 2 pm
  14. COMPLETED – Empire Blvd WB lane shift between Achillies Way and Zeus Way for asphalt patching. Jun. 24; 8:30 am – 3:30 pm
  15. COMPLETED – Queen Creek Rd EB and WB lane shift between 212th ST and Crismon Rd for asphalt repair. June. 25; 11 pm – 5 am
  16. COMPLETED – Hawes Rd full closure between Germann Rd and Ryan Rd for asphalt overlay. Jun. 25; 7 am – 3:30 pm
  17. COMPLETED – Ocotillo Rd EB and WB lane shift between Barnes Pkwy and Meridian Rd for pavement repairs. Jun. 26; 8:30 am – 3:30 pm
  18. COMPLETED – Hawes Rd full closure at the intersection on Queen Creek Rd for pavement repair. Jun. 27; 11 pm – 5 am
  19. COMPLETED – Maya Rd full closure at the intersection on Ellsworth Loop Rd for pavement repair. Jun. 27; 11 pm – 5 am
  20. Ellsworth Rd SB lane shift between Ocotillo Rd and Chandler Heights Rd for pothole and bore work. Jun. 26 – Jul. 02; 9 am – 2 pm
  21. COMPLETED – Cloud Rd WB lane shift between Crismon Rd and 214th St for asphalt and concrete work. Jun. 24 – Jun. 28; 24-hour

Comments