San Tan Valley Transportation Project Update

Gary Road

After closure due to a sinkhole for five days, Gary Road, west of Hunt Highway, reopened Thursday afternoon.

Magma Road 

Hunt Hwy to Gary Rd: Project tentatively scheduled for starting construction late 2019. Germann Road – Ironwood to Meridian Rd: anticipate project starting late Summer 2019

Ocotillo Road Rehabilitation

Ironwood to Kenworthy: Pavement restoration project and a new traffic signal at Cambria Drive intersection. Project to start early March 2019, estimated construction duration 150 days.

Gary Road Widening Improvements

End of Town of Queen Creek Project to Empire Blvd: Tentatively scheduled for construction to begin Summer 2019 

Meridian Road

Germann Road to SR24: IGA completed with the Town of Queen Creek, design kickoff in January 

Meridian Road

Germann Rd to Riggs Rd/ Combs Rd: IGA completed with the Town of Queen Creek, construction tentatively scheduled for FY21/22 depending on funding 

Traffic Engineering Improvements: 

Poston Butte High School speed feedback signage – complete. Champion School Speed Feedback Signage (Bella Vista Rd) – completion end of March (still awaiting Johnson Utilities sewer work in the area)